Project Description:
We were pleased to secure this fast paced small works project from KIER, our package included widening the existing entrance / exit road, creating traffic islands, installing multiple ducting runs to allow for installation of parking barriers to the unique surroundings of Wakehurst Place in Ardingly.
This project was scheduled to be completed in 4 working weeks and through a dedicated workforce and close co-operation with KIER and Kew Garden management we completed the works a week ahead of schedule. This was all done whilst working around live very heavy visitor usage of 2500 – 3000 cars/coaches a day using the same entrance / exit being worked on at this unique centre.